LD-SHELF-RTL-BRIDGE) charges interest only on disbursed funds rather than the full undrawn rehab reserve, saving borrowers thousands during construction. Arranged by Loan Daddy LLC (NMLS #2827624 · [email protected]).| CSI Division | Construction Trade / Line Item | Inspection Draw Stage | Line-Item Budget ($) | % of Rehab |
|---|---|---|---|---|
| Div 02 | Demolition, Hauling & Dumpsters | Draw Stage #1 | 4.1% | |
| Div 03 | Foundation, Concrete & Structural | Draw Stage #1 | 5.5% | |
| Div 06 | Rough Framing & Subfloor Carpentry | Draw Stage #1 | 6.8% | |
| Div 07 | Roofing, Fascia & Gutters | Draw Stage #2 | 8.6% | |
| Div 22 | Plumbing Rough-In, Re-Pipe & Water Heater | Draw Stage #2 | 5.9% | |
| Div 26 | Electrical 200A Panel & Re-Wire | Draw Stage #2 | 5.5% | |
| Div 23 | HVAC Condenser, Ductwork & Mini-Splits | Draw Stage #2 | 7.3% | |
| Div 09A | Insulation, Drywall & Interior/Exterior Paint | Draw Stage #3 | 8.2% | |
| Div 09B | LVP Flooring, Tile & Baseboards | Draw Stage #3 | 7.7% | |
| Div 12A | Kitchen Shaker Cabinets, Quartz & Appliances | Draw Stage #3 | 13.2% | |
| Div 12B | Bathrooms, Vanities, Tubs & Tile Surrounds | Draw Stage #3 | 8.6% | |
| Div 08 | Low-E Windows, Sliders & Entry Doors | Draw Stage #2 | 5.9% | |
| Div 32 | Stucco/Siding, Driveway & Landscaping | Draw Stage #4 | 4.5% | |
| Div 01A | Permits, Architecture & Engineering Plans | Draw Stage #1 | 2.3% | |
| Div 01B | 10% Hard-Cost Contingency Reserve | Draw Stage #4 | 5.9% |
Submit your 15-trade SOW to Loan Daddy LLC (NMLS #2827624 · (480) 485-1229) for 85%–90% purchase + 100% rehab holdback on a Non-Dutch drawn-balance shelf.